Support max up to 8 racks!(192 servers)
- When you add a new rack some redundant spine switch are added to interconnect racks.
Hosts:
- Min 4 hosts management
- Min 4 host infrastructure
Here are some information on the physical requirements for Cloud foundation:
- Redundant power
- 8 to 24 VSAN ready nodes
- Management switch
- 48 x 1GB
- Redundant Top-of-Rack switches
- 48 x10GB
- 4 x 40GB (2 to each switch)
- Redundant Spine switches (only require if more than 1 rack)
- Multi rack config
- 32 x 40Gbps
Network architecture:
- Automated installation and configuration of physical networking.
- Integrates with existing data center network infrastructure
- Uplink fully compatible to existing switches (Cisco, juniper)
- vMotion shared across all workload domains
- VXLAN shared across all workload domains
- Different VLANS for each network
Different VLANs created for each workload domain:
- Non-routable management VLAN
- Public management
- Corporate external
- VSAN
- vMotion
- VXLAN
Switch count for 1 rack?
- 1 x management switch
- 2 x top-of-rack switches
Switch count for 2 racks?
- 1 x management switch
- 2 x top-of-rack switches
- 2 x spine switches
VMware will also be providing a wire map for implementations.